Labor proposal · scope of work · materials schedule

First bedroom package

Repair and support the damaged floor below the bathroom, then finish the first bedroom, hallway and two closets—including the windows, floor, walls, trim, paint and electrical work.

Project approach. Each section is a separately priced work package. Work outside the stated scope will be discussed and approved before additional labor or cost is incurred.

Matt performs the work. A helper is planned only for the two window installations and the finished flooring installation.

$6,500Total labor
4–5Estimated weeks
3Priced sections
5Progress draws

Work packages and price


Section Afirst

Bathroom-floor joist repair and support

$1,500

Labor only · approximately 2–3 working days

Section Bfinishes

First bedroom, hallway and two closets

$4,000

Labor only · approximately 9–12 working days

Section Crough + trim

Bedroom and hallway electrical

$1,000

Labor only · approximately 3 working days

Section A includesbathroom area

The goal is to safely lift and support the low area below the bathroom, rebuild the strength lost where the joist was cut, and keep that repair supported while the rest of the house is evaluated later.

  • Set temporary supports and slowly lift the damaged bathroom-floor area toward its proper position.
  • Install a full-size new board tight alongside the joist damaged by the plumbing. This is the sister board.
  • Install short cross boards between the joists on both sides of the repair and secure them with Simpson hangers.
  • Run a horizontal support board underneath those cross boards, then fasten the sister, cross boards and lower support together so they work as one reinforced section.
  • Install and secure the planned adjustable support columns.
  • If an obstruction prevents the sister board from resting properly at the block wall, install the included backup 4×4 post from the floor to the repaired framing. It will have a base at the floor and a wall bracket to keep it straight and in position.
  • Leave the repaired framing exposed for the owner's builder brother to review before it is treated as the permanent repair.

Limit: This section stabilizes the immediate bathroom area. It does not level the entire house or correct the separate rear-house slope.

Section B includescomplete room

This section takes the first bedroom, short hallway and both closets from their present condition through a finished, painted room with a new floor and two installed windows.

  • The first bedroom, approximately 10-foot hallway, bedroom closet and hallway linen closet.
  • Rebuild both closets.
  • Cover the solid existing plaster with new drywall, and repair the access cuts and screw holes made during the work.
  • Clean and bond the old plaster repair areas, fill the deeper repairs with Durabond 45, reinforce the joints and finish them with compound that can be sanded smooth.
  • Skim and smooth the existing ceiling so it has an even finished surface.
  • Correct the worst low spots, then install a new tongue-and-groove subfloor surface to provide a fresh, flat base for the finished flooring.
  • Install the selected carpet or laminate finished flooring.
  • Remove and install two replacement windows.
  • Install basic interior base, window, door and closet trim.
  • Apply PVA primer and final wall/ceiling/trim paint.

Limit: The bathroom itself, custom millwork, exterior siding/masonry work and substantial window-opening reconstruction are not included.

Section C includes3 labor days

This section replaces the bedroom's outdated wiring with the planned outlets, lights and fan connection, adds the hallway light, and runs the new wiring back to the existing electrical panel.

  • Approximately 6–8 bedroom wall outlets.
  • A properly rated ceiling-fan box and wall control.
  • Approximately 4–6 cut-in lights.
  • One hallway light and one hallway switch.
  • Run the bedroom and lighting wiring back to the existing panel.
  • Install the boxes and wiring first, then install the outlets, switches and lights and perform basic final testing.
  • The hidden wiring is installed before Section B closes and finishes the affected walls and ceiling.
  • Plaster/drywall repair created by the agreed electrical routes is finished under Section B.

Limit: Panel replacement, service upgrade, repair of unrelated existing wiring and routes extending into additional rooms are not included.

Concept drawings


Review point. These drawings show where the new boards and supports are intended to go; they are not based on final job-site measurements. Board sizes, support points, obstructions and connector fit will be checked with the framing exposed.

Drawing 1 — Plan view of localized joist repair

Plan view of localized joist repairExisting joists, damaged joist, new sister, crossmembers, support line and block wall. block-wall bearing existing joistdamaged joistexisting joist removed / plumbing-damaged section full-depth crossmembersfull-depth crossmembers continuous sister: crossmember line to wall bearing lower support member beneath this line
existing framingnew sistercrossmemberslower support linedamaged void
The new sister bears at both ends. Crossmembers are installed inside the joist spaces. The lower horizontal support sits beneath the crossmember line, and the three elements are tied together as one localized support assembly. No loose steel plate is planned beneath the void.

Drawing 2 — Elevation of lower support and wall contingency

Elevation of support assemblyFloor above, joists, sister, lower support, adjustable supports and optional wall-side four by four. bathroom floor above sister and tied crossmember assembly horizontal support member below crossmembers basement slab / verified bearing surface optional 4×4 wall-side postonly if direct joist bearing is blocked
existing structurenew tied framinglower supportcontingency 4×4
Adjustable supports provide the localized lift and support. The optional wall-side 4×4 is included in Section A labor if obstruction prevents the sister from obtaining the intended wall-side bearing.

Drawing 3 — Bedroom/hallway floor build-up

Floor flattening and overlay detailExisting floor, fixed tapered sleepers and shims, tongue and groove subfloor and finish flooring. retained sound subfloor after fastening and repairs fixed tapered sleepers/shims over joist lines where required new 23/32-in. T&G subfloor surface selected carpet or laminate finish flooring target flat plane
Localized sleeper/shim correction follows Section A. The goal is a flat plane for the new T&G layer and finished flooring; this is not an attempt to level the entire house.

Payment schedule


DrawExpected progress checkpointAmount
1Section A bathroom-floor joist repair and support completed.$1,500
2One week later: electrical wiring and room preparation substantially underway.$1,000
3Following week: window, closet and subfloor work substantially underway.$1,000
4Following week: drywall, plaster repair and ceiling-smoothing work substantially underway.$1,000
FinalFinished flooring, trim, paint, outlets, switches, lights and agreed punch list completed.$2,000
Total labor$6,500

The section prices define the work. The draws establish the expected weekly payment schedule; individual tasks may shift between weeks as the work is sequenced.

Changed conditions and additional scope


No automatic extras. If one of the following conditions appears, work at that point pauses long enough to discuss the effect on method, schedule and price. Additional work begins only after agreement.

Structure and floor

  • Damage extends beyond the identified bathroom joist or affects several joists.
  • Hidden rot, insect damage, crushed wood or a failed wall-top/support point is uncovered.
  • The block wall or basement floor cannot safely hold the planned bracket or support.
  • Plumbing, ductwork or wiring blocks the agreed board and support layout.
  • The floor, walls or finishes move, crack or bind unexpectedly while the floor is being lifted.
  • The larger house slope prevents us from making the bedroom and hallway reasonably flat within this section.

Walls, windows and electrical

  • Much more plaster or paint is loose than can presently be seen.
  • Removing a window uncovers rot, a damaged support above the window or an opening that must be rebuilt.
  • The selected flooring needs substantially different preparation than planned.
  • The planned wiring path through the ceiling or walls is blocked and requires additional openings or work in another room.
  • The existing panel or old wiring needs repair or replacement beyond the circuits listed here.
  • Hazardous or unknown material is found and needs separate handling.

Owner-supplied items


The $6,500 is labor only. The owner supplies all building materials, hardware, fixtures, finishes, fasteners, adhesives and job-specific consumables.

This includes lumber, drywall, subfloor, flooring, windows, connectors, supports, anchors, electrical equipment, wire, devices, lights, paint, trim, drill/masonry bits, saw and masonry blades, grinding discs, sanding blocks/screens, tape, plastic, caulk, rollers and brushes. Ordinary reusable hand and power tools are included with labor. Any specialty rental is discussed first.

Materials — Section A order first


Home Depot catalog identifiers were checked September 5, 2026. Public pages did not reliably expose Burton #2717 shelf quantities; verify same-day stock in the Home Depot app or with the Burton Pro Desk at 810-715-2402.

QtyItemModel / partHome Depot identifiersTiming
4No. 2-or-better 2×10×8 lumber; match actual joist depthWOOD — field matchBurton lumber deskorder now
2Straight No. 2-or-better 4×4×8 posts: lift/support allowance plus wall contingencyWOOD — field cutBurton lumber deskorder now
2No. 2 2×4×8 for temporary bracing/cleatsWOODBurton lumber deskorder now
4Simpson double-2×10 face-mount joist hangerLUS210-2ZInternet 100375371
SKU 669452
order now
2 + 4 conditionalSimpson single-2×10 face-mount joist hangerLUS210ZInternet 100375106
SKU 865889
order / return spare
1 box / 100Simpson Strong-Drive SD connector screws, #9 × 1½ in.SD9112R100Internet 202071152
SKU 477314
order now
1 box / 100Simpson Strong-Drive SD connector screws, #9 × 2½ in.SD9212R100-RInternet 206101818
SKU 478811
order now
1 box / 50Simpson Strong-Drive framing screws, 0.160 × 2½ in.SDWS16212QR50Internet 321563388order now
4 tubesPremium polyurethane construction adhesive for sister contactField-selectedVerify label and Burton stockorder now
1Husky 6-ton hydraulic bottle jack; lifting onlyHPL6BInternet 308174827
SKU 754902
order now
Up to 3Permanent-rated adjustable steel building-support columns; exact model requires installed heightHEIGHT HOLDExample only: Tiger 3A-66610, Internet 202086524, SKU 746626; fits 78–82 in. onlymeasure first

Section A contingency items


QtyItemModel / partIdentifier / sourceReason
1Simpson adjustable 4×4 post baseABA44ZHD Internet 100374999
SKU 669421
Wall-side 4×4 contingency
1 pairSimpson adjustable 4× post capAC4ZHD Internet 100375176
SKU 669439
Positive post-to-support connection
As selectedWall-side lateral keeper/collar for the 4×4FIELD MATCHNo part assigned until clearances and bracket-hole pattern are knownPrevents lateral/outward post movement
Small packSimpson Titen HD anchor for verified solid/grouted masonryTHD37300HF1
⅜ × 3 in.
HD Internet 300690800
SKU 1002236974
Use only if substrate and bracket match
1 cartridgeSimpson SET-3G high-strength anchoring epoxySET3G10HD Internet 312947523
SKU 1005261153
Hollow-block contingency; return if unopened
3Gray Simpson Opti-Mesh screen tubes for ⅜-in. threaded rod3GWS373P or 3GWS376PStructural fastener supplier; length follows verified block geometryRequired when an anchor location opens into hollow CMU
3⅜-in. clean threaded rods with washers and nutsMATCH SCREEN / BRACKETField-cut only after embedment and projection are setHollow-block contingency

Contingency products may be returned if not required and still returnable. Do not substitute a lead shield or ordinary wedge anchor for the hollow-block system.

Materials — Section B, order after measurements


QtyItemModel / partHome Depot identifiersTiming
Area ÷ 32 + 10%23/32-in. APA-rated T&G plywood/OSB subfloorWOOD — final selectionField measure bedroom + hallwayphase B
Per sheet layoutLiquid Nails Subfloor and Deck, 28 oz.LNP-902Internet 202203997
SKU 515581
phase B
Area ÷ 32 + 10%½-in. USG Sheetrock UltraLight drywall14113411708Internet 202530243
SKU 893749
phase B
Field quantityLiquid Nails Drywall Advanced, 28 oz.DWP-40Internet 309460978
SKU 1004508309
phase B
1 box / 5 lbGrip-Rite #8 × 2½-in. coarse-thread drywall screws212CDWS5Internet 100113786
SKU 757479
phase B
1 bagUSG Sheetrock Durabond 45, brown bag, 25 lb.USG 381110Not confirmed on current Home Depot shelf listing; drywall supply may be requiredphase B
1 / 4 lbDAP Plaster of Paris, white dry mix10318Internet 100126904
SKU 106225
phase B
1 gallonLarsen Plaster-Weld bonding agentPWG04Paint/drywall supplier; not confirmed at Home Depot Burtonphase B
1 pailUSG green-lid All Purpose ready-mixed joint compound, 4.5 gal.380501Internet 100321605
SKU 258725
phase B
1 rollUSG paper joint tape, 2-1/16 in. × 250 ft.382175Internet 100321613
SKU 258423
phase B
1 rollFibaTape fiberglass mesh, 1-7/8 in. × 300 ft.FDW8665-UInternet 100429159
SKU 483689
phase B
1 rollFibaTape metal drywall corner tape, 100 ft.FDW6622-UInternet 100266369
SKU 349995
phase B
1 / 5 galKILZ PVA white interior drywall primerPX01005Internet 202665645
SKU 454089
phase B
23M 120-grit fine drywall sanding sponge30904FInternet 202074118
SKU 752277
phase B
1 / 10 pack3M 120-grit drywall sanding screens99438Internet 100321149
SKU 754038
phase B
AllowanceCoarse sanding blocks plus finer finish blocks/screensFIELD SELECTMatch to plaster removal and finish coatphase B
2Replacement windowsOWNER SELECTIONOrder from verified rough-opening measurementsmeasure first
Field quantityBasic trim, finish flooring and final paintOWNER SELECTIONStyle, color and quantity to be approvedselect later

Open item, intentionally not on the purchase list: locate an appropriate approximately 24–36-in.-wide fiberglass reinforcing mesh/fabric if broad plaster reinforcement is required.

Materials — Section C electrical allowance


Final breaker, conductor and device selections follow the existing panel and final circuit layout. The table identifies the principal owner-supplied products without locking the project into the wrong panel hardware.

QtyItemModel / partHome Depot identifiers
10Carlon 1-gang 20-cu.-in. old-work PVC boxesB120RInternet 202077323 · SKU 141206
1Westinghouse retrofit ceiling-fan Saf-T-Brace0140000Internet 204845573 · SKU 1007812589
4–6Commercial Electric 6-in. color-selectable canless LED kits91302Internet 306079881 · SKU 1003532011
1 rollSouthwire 250-ft. 12/2 copper NM-B with ground28828269Internet 202019375 · SKU 268844
1 / 10 packLeviton 15A tamper-resistant white duplex receptaclesM22-T5320-WMPInternet 100684043 · SKU 897912
As laid outSwitches, wall plates, cable staples, listed connectors and fixture selected for hallwayFIELD / OWNER SELECTMatch final color, gang count and control layout
As requiredCompatible breaker(s)PANEL MATCH ONLYIdentify the existing panel before purchase

Approval


By signing below, the owner approves the described labor scope, section prices and progress-draw schedule. Materials and expendables are owner-supplied. Changed conditions and work outside this scope will be discussed before additional labor or cost is incurred.

Owner / ClientDate
Matt SalemDate
Builder review — Section ADate
Review notes / revision reference